Y'ALL, City Hall

Austin City Council ★ decoded daily ★ keep council weird ★ every claim links to its source

← Thursday, May 28, 2026

Item 12 Passedunofficial

Authorize additional contingency for the construction contract for the Northwest Lift Station Improvements: Rock Harbor Force Main and Four Points #2 Project for Austin Water with Santa Clara Construction, LTD, to increase the amount by $537,225, for a total contract amount not to exceed $5,280,171. Funding: $537,225 is available in the Capital Budget of Austin Water.

This authorizes an extra $537,225 in contingency funding for the ongoing construction of the Rock Harbor Force Main and Four Points #2 wastewater project, part of Austin Water's Northwest Lift Station improvements. The boost would push the total contract with Santa Clara Construction to no more than $5,280,171, with the money coming from Austin Water's capital budget. Lift stations and force mains keep wastewater flowing through the system, so projects like this affect service reliability in the area.

budget

"without objection, the consent agenda is adopted" — meeting transcript (unofficial)

Agenda PDF Legistar Official votes