Item 15 Passed 11-0

Authorize a contract for construction services for the West Bouldin Creek - Del Curto Storm Drain Improvements and SOLA-C3.005 Intersection Improvements Bluebonnet Lane and Del Curto Road project with Santa Clara Construction, Ltd., in the amount of $8,781,522, plus a $878,153 contingency, for a total contract amount not to exceed $9,659,674. Funding: $9,080,093 is available in the Capital Budget of the Watershed Protection Department, $579,581 is available in the Capital Budget of the Transportation and Public Works Department.

The roll call

Approved on Consent 11-0

  • Kirk Watson Mayor Yes
  • Natasha Harper-Madison D1 Yes
  • Vanessa Fuentes D2 Yes
  • José Velásquez D3 Yes
  • José "Chito" Vela D4 Yes
  • Ryan Alter D5 Yes
  • Krista Laine D6 Yes
  • Mike Siegel D7 Yes
  • Paige Ellis D8 Yes
  • Zohaib "Zo" Qadri D9 Yes
  • Marc Duchen D10 Yes

Official votes