Item 20 Passed 11-0
Authorize execution of a contract for construction services, for Austin Water and to be managed by Capital Delivery Services, for the Northwest Area Lift Station Improvements: Boulder Lane Lift Station project with C.C. Carlton Industries, Ltd., in the amount of $6,881,000, plus a $688,100 contingency, for a total contract amount not to exceed $7,569,100. Funding: Funding is available in the Capital Budget of Austin Water.
The roll call
Approved on Consent 11-0
- Kirk Watson Mayor Yes
- Natasha Harper-Madison D1 Yes
- Vanessa Fuentes D2 Yes
- José Velásquez D3 Yes
- José "Chito" Vela D4 Yes
- Ryan Alter D5 Yes
- Mackenzie Kelly D6 Yes
- Leslie Pool D7 Yes
- Paige Ellis D8 Yes
- Zohaib "Zo" Qadri D9 Yes
- Alison Alter D10 Yes