Item 43 Passed 11-0

Authorize execution of a contract for construction services for Austin Energy for the Decker Power Plant - Dam Upgrades Reissue project with MortMara Construction, Inc., d/b/a McMillen, Inc., in the amount of $12,198,059 plus a $1,801,941 contingency, for a total contract amount not to exceed $14,000,000. Funding: Funding is available in the Fiscal Year 2025-2027 Operating Budget of Austin Energy.

The roll call

Approved on Consent 11-0

  • Kirk Watson Mayor Yes
  • Natasha Harper-Madison D1 Yes
  • Vanessa Fuentes D2 Yes
  • José Velásquez D3 Yes
  • José "Chito" Vela D4 Yes
  • Ryan Alter D5 Yes
  • Mackenzie Kelly D6 Yes
  • Leslie Pool D7 Yes
  • Paige Ellis D8 Yes
  • Zohaib "Zo" Qadri D9 Yes
  • Alison Alter D10 Yes

Official votes