Item 19 Passed 10-0
Authorize execution of a contract for construction services for the Oltorf Street Reclaimed Water Main Phase 2 project with Cash Construction Company, Inc., in the amount of $10,401,106 plus a $1,040,111 contingency, for a total contract amount not to exceed $11,441,217. [Note: This contract will be awarded in compliance with City Code Chapter 2-9A (Minority Owned and Women Owned Business Enterprise Procurement Program) through the achievements of Good Faith Efforts with 2.42% MBE and 0.08% WBE participation].
The roll call
Approved on Consent 10-0
- Kirk Watson Mayor Yes
- Natasha Harper-Madison D1 Absent
- Vanessa Fuentes D2 Yes
- José Velásquez D3 Yes
- José "Chito" Vela D4 Yes
- Ryan Alter D5 Yes
- Mackenzie Kelly D6 Yes
- Leslie Pool D7 Yes
- Paige Ellis D8 Yes
- Zohaib "Zo" Qadri D9 Yes
- Alison Alter D10 Yes